Bookmark Creek Complex
SRE Bookmark Creek project
As one of the 3 identified sites under the $37.6 million Sustaining Riverland Environments (SRE) program, the Bookmark Creek project focuses on reinstating natural habitat conditions in the Bookmark Creek Complex.
Located around Renmark, Bookmark Creek is an 8 km anabranch that bypasses Lock 5, along with 13 km of the River Murray main channel in South Australia. The First People of the River Murray and Mallee Region are the Traditional Owners of the Bookmark Creek region, with the presence of Aboriginal cultural heritage providing tangible links to both ancestors and Country.
Originally a natural creek depression that flowed during periods of high river flows, Bookmark Creek underwent significant changes instigated by European colonization, which brought with it development of the first Australian irrigation district in the late 1880s. This was followed by construction of Lock 5 in 1927 which following construction, resulted in permanent inundation at the inlet. These changes meant the creek was used as a reservoir to supply irrigation water, then later as an irrigation disposal basin.
The combination of these factors has had adverse impacts on the ecological values of the site and contributed to environmental degradation of the landscape over time.
Following a holistic ecological and hydrological assessment undertaken with continued stakeholder engagement, possible infrastructure and management solutions have been identified. These have been considered in the context of other opportunities emerging in the region which forms the Sustaining Riverland Environments program.
Project objective
The Bookmark Creek Complex project aims to contribute environmental, social, cultural and economic benefits to support the growth and wellbeing of the community. It offers a unique opportunity to create high-value, fast-flowing habitat conditions within the creek, which are important for a number of large-bodied native fish species. It will also improve fish passage through the creek by addressing numerous structures that currently impede fish movement along the creek.
Importantly, the broader complex (encompassing areas from the Ral Ral Floodplain to Disher Creek, including wetlands along the creek and surrounding floodplain) has extremely high social and recreational value to the regional community. Support for the project from local industry, key stakeholders and landholders, as well as some active and well-established community groups, provides a strong foundation for future works in the area.
Consultation and design
Extensive consultation has been undertaken with key stakeholders, including:
- September 2021: Workshop 1 – Outcomes and design basis
- October 2021: Workshop 2 – Design options presented
- November 2021: Workshop 3 – Design refinement session
- February 2022: Workshop 4 – Presentation of 70% designs
- July 2022: Workshop 5 – Presentation of 90% designs and Wetland Management Plan
In workshop 4 and 5, detailed designs were unveiled and endorsed and included:
- 3D modelling of the Jane Eliza inlet regulator and Nelwart Street Bridge, and sections of creek designated for ‘re-snagging’ to provide vital woody habitat for native fish, such as the Murray cod.
Works to be undertaken
The Bookmark Creek Complex project program of works includes:
- construction of an inlet regulator adjacent Jane Eliza Estate
- construction of a bridge at Nelwart Street and Twentysixth Street. replacing 2 pipe structures on Bookmark Creek with new infrastructure that can substantially increase the flow of water down the creek
- incorporating fish-friendly infrastructure to reinstate connectivity between Lock 4 and Lock 5 weir pools.
- reinstate a more natural creek morphology and large woody habitat for native fish
- upgrade infrastructure at managed wetland sites adjacent to the creek to improve their function and integrate their operations with weir pool manipulation and high flows.
These works will enable the following environmental outcomes:
- improved fast flowing habitat for large bodied native fish
- enhanced environmental outcomes from increased hydraulic diversity and connectivity for fish
- enhanced social, economic and recreational benefits associated with improved connectivity, amenity and condition of high value wetlands/floodplains.
The construction tender for the project was awarded to Fulton Hogan Constructions, with works beginning at both Bookmark Creek inlet regulator and Nelwart Street Bridge sites in late October 2024. Works are anticipated to be completed within 12 months (late 2025).
For queries regarding construction at Bookmark Creek, please email bookmarkcreek@fultonhogan.com.au or phone 1800 417 686.
More Information
Get involved
We are committed to working with First Nations people, local communities and the broader South Australian community throughout the life of the SRE program.
Subscribe to the River Murray SA newsletter for updates and SRE engagement opportunities.
- Email us at dew.sreprogram@sa.gov.au
- Call the Department for Environment and Water (DEW) on (08) 8204 1910.
Department for Environment and Water (DEW) social media
Resources
SRE project pages
Weir pool manipulation
Other resources
- SA River Murray Flow Report
- Constraints Management Strategy
- Murray-Darling Basin Authority
- Murray-Darling Communities Investment Package
- MDBA Water Recovery Strategy
- South Australian Riverland Floodplains Integrated Infrastructure Program (SARFIIP)
- The Ramsar Convention on Wetlands
The Sustaining Riverland Environments Program is a $37.6 million program funded by the Australian Government through the Murray-Darling Basin Authority and delivered by the Government of South Australia through the Department for Environment and Water.