Can I clear native vegetation to establish or maintain a recreation track?

You can clear vegetation to establish or maintain a track for public recreational use for non-motorised vehicles, such as bicycles or horses.

Does this include land under Heritage or Management Agreement?

Yes you can clear for this purpose on Heritage Agreement or Management Agreement land only if the terms of the Heritage Agreement or Management Agreement permit clearance.

Do I need approval?

Yes you need to get approval from the Native Vegetation Council (NVC).

What do I have to do?

  • Make sure that your proposed clearance is within the parameters of this activity.

  • Consider if there are other practical alternatives to clearing, such as positioning a new track so that it involves no clearing, or clearing vegetation that is less significant or more degraded.

The NVC will assess the level of risk to biodiversity associated with your clearance proposal.

If your proposal is assessed as a ‘low risk’ activity (Level 1 of the Risk Assessment)

Your proposed clearance will be considered low risk if it is for 500m2 or less of vegetation, or 5 or fewer scattered trees. Although in the pastoral areas of the state (i.e. NRM Regions South Australian Arid Lands and Alinytjara), the vegetation proposed to be cleared can be up to 3 hectares.

You will need to provide the following to the NVC:

  • an online application identifying the
    • regulation that applies to your situation
    • measures taken to avoid and minimise the proposed clearance
    • number and size of any scattered trees to be cleared
    • size of vegetation patch to be cleared
    • any previous clearance history
  • photographs of the site.

The NVC will assess the information against the Mitigation Hierarchy and the requirements of the regulation (you can see these in detail in the Native Vegetation Regulations 2017). If the NVC is satisfied, the NVC will issue an approval and a Significant Environmental Benefit (SEB) offset of $500 will be required.

If your proposal is assessed as a ‘medium to high risk’ activity (Levels 2, 3, and 4 of the Risk Assessment)

If your proposed clearance does not meet the criteria for low risk (Level 1), you will be required to engage an Accredited Consultant to undertake a vegetation assessment of the proposed clearance area. The consultant will prepare a Data Report which must be submitted in addition to the information required for ‘low risk’ applications.

If any of the following escalating factors are identified in the risk assessment, the proposal will be automatically raised to the next level (i.e. 2, 3 or 4) of risk and an SEB offset will be required. If there:

What are my obligations if I am granted approval?

  • Undertake clearance within 2 years of approval being granted, unless otherwise specified.
  • Undertake clearance in compliance with any conditions that apply which are binding and enforceable against the person to whom the approval is granted as well as subsequent owners and occupiers of the land.

What if I want to clear vegetation to establish or maintain a private recreation track?

You can clear vegetation to establish or maintain a track on private land for walking.

What if I want to clear vegetation to establish or maintain a vehicle track?

You can clear vegetation to maintain an existing or establish a new vehicle track.

Exclusions

You are not permitted to clear under this activity if you are:

  • clearing vegetation previously established as a condition of a consent for clearance or under regulation (including a condition in respect of clearance permitted under revoked regulations).

What if my activity doesn't fit this description?

If your proposed clearance does not meet the requirements of this regulation, or another regulation, you can submit a clearance application under Section 28 of the Native Vegetation Act 1991.

Contact

Native Vegetation Branch.